Failed gasified coal project brings request from utility

CARSON CITY -- Sierra Pacific Power Co. asked Nevada regulators for authority to collect $42 million from ratepayers for a clean-coal generating experiment that failed -- but opponents said Friday the request should be denied and the utility should refund $50 million it already got.

There was no immediate decision by the state Public Utilities Commission on the request involving Sierra's Piñon Pine gasified coal project. A PUC spokesman said a ruling would be issued following a review of the testimony Friday and voluminous paperwork filed in the case.

During the hearing, Phil Williamson of the state Bureau of Consumer Protection detailed costs involving the project, which already has received more than $200 million in taxpayer and ratepayer dollars, and said the bureau wants a $92 million disallowance.

When asked by Sierra Pacific attorney Julia Sullivan to elaborate on the proposed disallowance, Williamson said it represented $50 million the Reno-based utility already received plus the $42 million it's trying to get the PUC to approve.

Sullivan questioned the accuracy of the figures the consumer advocate's office presented, once saying she was "startled and stunned" by some of the numbers.

Sierra Pacific Power attorneys also said the utility's decision to try the gasification technology was "prudent as a matter of law" and Sierra is entitled to recover all its "just and reasonable costs."

But the consumer advocate's office, headed by Eric Witkoski, said the request for $42 million should be rejected because the utility already has been allowed enough recovery, and $50 million that was authorized previously should be refunded to customers.

More than half of the funding for the Piñon Pine gasified coal project came from the federal Department of Energy. That agency's records show it's a prime example of investments of public funds in failed alternative energy ventures around the nation.

Construction on the Piñon Pine project, part of the utility's Tracy power station east of Reno, started in early 1995. The project, plagued by cost overruns, came on line in late 1996, but as a conventional, gas-fired power plant. The experimental gasified coal system was shut down. Total costs for the entire plant ran more than $340 million.

Sierra Pacific Power continues to run the conventional side of the plant, and is expanding other gas-fired generating facilities at its Tracy station.

Besides the $168 million the Reno-based utility got from the federal Energy Department, Sierra Pacific already has been authorized by the PUC to collect more than $110 million from its ratepayers for both the conventional and experimental Piñon Pine projects.

The commission previously denied Sierra Pacific's request for the additional $42 million. But the utility appealed and won a court order in 2006 that led to the new commission hearings.

Because the money Sierra seeks would be collected over several years, the effect on customers' monthly bills would be slight. If the company wins its latest request, the average residential customer would pay only a few dollars more per month.

THE LATEST
‘Trop dust’: Air quality advisory issued for Tropicana demolition

The Clark County Division of Air Quality has issued an air quality dust advisory during the early hours of Wednesday, as the Tropicana casino-hotel implosion will “produce a cloud of ‘Trop dust.’”

Allegiant Stadium to host Gold Cup soccer matches

Two international soccer matches will be played at the 65,000-seat Allegiant Stadium next summer, according to an agreement approved by the LVCVA on Tuesday.

Las Vegas homes sitting on the market longer as sales drop

Supply continues to outpace demand as Las Vegas Valley homes are sitting on the market longer without offers, according to Las Vegas Realtors statistics.

Allen, Hard Rock ready to take on Las Vegas

The casino resort — which is being built on the grounds formally occupied by the Mirage casino-hotel — is tentatively scheduled to open sometime in 2027.